News

Operating schedule announced: berth No. 1 from April 2026, berth No. 2 from August 2026

The port is operating berth No. 1 on a temporary basis from April 2026 and berth No. 2 from August 2026, with the whole investment and construction process expected to finish in Q1 2027. Bringing the port into early operation to handle import-export cargo for local businesses brings greater advantages to Quang Tri’s economy.

Hon La Port self-funds a shared channel for vessels up to 70,000 DWT (lightened)

Groundbreaking of Hon La International Multi-purpose Port

Berth No. 1 welcomes its first vessel from Germany

After just one year of construction, berth No. 1 is in operation and berth No. 2 has completed more than 80% of the work.

Channel dredging and completion of the coal handling system

Channel dredging has passed 86% of volume, and the coal conveyor system is undergoing trial runs before handover.